In the future when new or revised priority list for county and city contract projects are received, each project should be reviewed and a summary sheet provided, showing a preliminary estimate of cost and needs evaluation. This information should be furnished as soon after receipt of the new list is practical.
The following guidelines should be used in completing the Summary.
| Columns 1-4 | - | Self-explanatory |
| Column 5 | - | "Existing Conditions" Poor alignment; heavy-light drainage; heavy-light grading; culvert; bridges, etc. |
| Column 6 | - | "Proposed Construction" Grading & Drainage; base & surfacing; culvert; resurfacing; County to grade & drain; etc. |
| Columns 7 & 8 | - | Self explanatory |
| Column 9 | - | This is a preliminary estimated cost only, and it is not expected, nor intended that a detailed estimate be prepared at this time. If the estimated cost is for type contract (LET, ASPHALT AGREEMENT, MATERIALS COST, ETC.) other than the estimate type listed at the top of the summary sheet, the type contract should be listed adjacent to the "preliminary estimate" |
It should be noted that a separate "Needs Number" and "Preliminary Estimate" should be provided in the ocation on the summary sheet for additional information if
It is further requested that appropriate sketches be attached showing the location and limits of each priority.