5 Phase Process for Solicited Proposals:
Phase I |
Phase II |
Phase III |
Phase IV |
Phase V |
Evaluation Phase Activities |
Committee Recommendations |
Board Consideration of LOI |
Development Phase Activities |
Final Contract Negotiations |
Phase I – Evaluation Phase Activities
- Department Screening Process
- 30 day public comment period to accept suggestions on solicitation of projects
- Department will determine the feasible projects for either a conceptual or detailed solicitation.
- Pre-Submittal Conference
- Department will advertise RFP, either conceptual (two-step) or detailed (one-step)
Conceptual RFP Process
- Conceptual Proposal Received within 60 days of RFP
- AC to determine if the Initial Qualifications of the proposal have been met
- Electronic executive summary for each qualifying proposal will be posted
- AC Initial Review
- AC Sub-Committees will rate the proposals
- Department will short list the highest ranked firms based on AC ratings
- Selected proposers will have 165 days to submit a detailed proposal
Detailed RFP Process
- Detailed Proposal Received within 165 days of RFP
- AC to determine if the Initial Qualifications of the proposal have been met
- Electronic executive summary for each qualifying proposal will be posted
- AC to conduct a Detailed Evaluation
- AC Sub-Committees will rate the proposals
- Department will short list the highest ranked firms based on AC ratings
- Proposers on the short list may be required to give an oral presentation
- AC will meet to make a proposal selection for further consideration
- AC taskforces will evaluate proposal and draft the LOI
- The AC review the LOI consideration/ recommendation to EC
Phase II – Committee Recommendations
- AC presents recommendation to EC
- EC evaluation of project and review of AC recommendation
- EC consideration review of LOI and recommendation to Board
Phase III – Board Consideration of LOI
- Board report to Governor, House and Senate Transportation Committees
- Non-proprietary proposal posted on Department’s website/ 15-30 day public comment period
- Board review of LOI and determination of whether to move forward with negotiations
- Department and Proposer Execute LOI
Phase IV – Development Phase Activities
- AC taskforce Negotiations of PFA/DSA
- PFA Execution
- DSA Execution
- Notice to Proceed
Phase V – Final Contract Negotiations
- CPPI Negotiations
- Department approval of all CPPI contracts (Design-Build; Finance Plan; Operations and Maintenance Agreement; etc.)
- Public Comment period before CPPI approval (30 Days)
- Board Review and vote on CPPI
- CPPI Execution by Department and Proposer
- Construction begins
Legend:
AC – Advisory Committee
CPPI – Contract for Public Private Initiative
DSA - Developer Services Agreement
EC - Evaluation Committee
LOI - Letter of Intent to Negotiate
LOITS - Letter of Intent to Submit
PFA - Project Framework Agreement
RFP – Request for Proposals