Notes:
(1) See current AASHTO Green Book, chapter 8, Design Speed. Also see notes 6,7, and 8 for design speeds not shown
(2) LOS C is permissible for urban conditions and auxiliary facilities in rural areas.
(3) LOS D is permissible in highly developed urban areas.
(4) Consider widening from existing 4 lanes to 6 lanes.
(5) On Freeways with six or more lanes and with truck traffic more than 250 vph, use 12-ft. inside shoulders.
(6) Values shown are for the given design speed. For other design speeds, refer to the AASHTOGreen Book, Chapter 3.
(7) Values shown are for the given design speed. For other design speeds, refer to the AASHTOGreen Book, Chapter 3.
(8) Values shown are for the given design speed. For other design speeds, refer to Chapter 4 of this Manual.
(9) Minimum values are for vehicular clearances. Please refer to the GDOT Bridge and Structures Design Policy Manual for further information, clearances at other facilities, and limitations.
(10) Minimum horizontal clearance equals to clear zone plus 4-ft. typical ditch.
(11) Refer to Section 6.10 for determination of width of required right of way. |